AS4000 construction contract review checklist

AS4000 is the Australian Standard general conditions contract widely used for commercial and civil projects. This checklist is for construction lawyers reviewing AS4000 before execution.

In short

This is a 12-step checklist for reviewing an AS4000 construction contract. It covers annexures, superintendent powers, payment, EOT, variations, and defects liability.

Run this checklist with Quillio — free trial
12-step checklist

The checklist

1

Review Annexure Part A

Check Annexure Part A for contract sum, dates, LD rates, security, and insurance.

2

Review Annexure Part B

Check Annexure Part B amendments for special conditions and departures.

3

Review superintendent role

Check the superintendent's role, dual function, and independence requirements under cl 20.

4

Check security and retention

Confirm security amounts, form, and release conditions under cl 5.

5

Review progress payment process

Check cl 37 payment claim, payment schedule and payment timing.

6

Check SOPA compliance

Confirm payment provisions comply with the state Security of Payment Act.

Building and Construction Industry Security of Payment Act 1999 (NSW)
7

Review variations clause

Check cl 36 variation process, pricing, and time bars.

8

Review EOT clauses

Check cl 34 EOT categories, notice requirements, and concurrent delay treatment.

9

Check practical completion

Review cl 34.6 practical completion definition and certification.

10

Review liquidated damages

Check the LD rate, cap, and application from practical completion.

11

Review defects liability period

Check cl 35 defects liability period length and rectification process.

12

Review dispute resolution

Check cl 42 dispute resolution — notice, conference, expert determination, arbitration.

When to use

When this checklist applies

Use when reviewing an AS4000 contract before principal or contractor execution.

Common pitfalls

  • EOT time bars missed due to strict notice requirements
  • Superintendent independence not addressed
  • Security release conditions unclear
  • LD cap not specified in Annexure Part A
  • SOPA compliance gap on payment schedule timing
Use with Quillio

Run this checklist on a real matter

Quillio can review an AS4000 contract, extract annexure departures, and flag SOPA gaps. See /practice-areas/construction-lawyers or start a free trial.

General guidance for AS4000 reviews. Adapt to project and amendments in Annexure Part B.