Home / Checklists / Construction extension of time claim checklist
AU · Construction

Construction extension of time claim checklist

EOT claims are commonly rejected for failure to comply with notice clauses or insufficient delay analysis. This checklist is for contractors and their lawyers preparing EOT claims under standard form contracts.

In short

This is a 12-step checklist for preparing a construction extension of time (EOT) claim. It covers notice, causation, delay analysis, and supporting evidence.

Run this checklist with Quillio — free trial
12-step checklist

The checklist

1

Identify the delay event

Identify the specific delay event and its start and end dates.

2

Check qualifying cause of delay

Confirm the event is a qualifying cause of delay under the contract.

3

Serve initial notice

Serve the initial notice within the contractual time bar — often 5 to 14 days.

4

Serve detailed claim

Serve the detailed EOT claim within the contractual period.

5

Identify critical path impact

Identify how the delay event impacts the critical path of the program.

6

Prepare delay analysis

Prepare a delay analysis — time impact, as-planned vs as-built, or window analysis.

7

Quantify days claimed

Quantify the number of extension days claimed on critical path impact.

8

Address concurrent delay

Address any concurrent contractor-caused delay per the contract terms.

9

Gather supporting evidence

Collect daily records, photos, weather records, subcontractor correspondence.

10

Attach programs

Attach baseline and updated programs showing critical path impact.

11

Prepare delay cost claim

Prepare any associated delay cost claim if the contract permits.

12

Submit and follow up

Submit to superintendent or principal and diarise response deadlines.

When to use

When this checklist applies

Use whenever a delay event arises that may entitle a contractor to an extension of time.

Common pitfalls

  • Missing the initial notice time bar
  • No critical path analysis
  • Concurrent delay not addressed
  • Delay analysis methodology unclear
  • Supporting records incomplete
Use with Quillio

Run this checklist on a real matter

Quillio can assemble an EOT claim from project records and program data. See /practice-areas/construction-lawyers or start a free trial.

General guidance for EOT claims. Apply the specific contract clauses and jurisdiction.

Use this checklist on your matter.

Quillio can run this checklist on a specific NSW conveyancing matter — confirm each item, calculate adjustments, and generate the supporting documents. The free trial requires no credit card.

Start your free trial