Construction progress claim review checklist

A principal, superintendent, or their advisor must review each progress claim against the contract, schedule of rates, and SOPA. This checklist is for construction lawyers and contract administrators.

In short

This is a 12-step checklist for reviewing a contractor progress claim as principal or superintendent. It covers entitlement, valuation, and payment schedule drafting.

Run this checklist with Quillio — free trial
12-step checklist

The checklist

1

Confirm claim receipt

Confirm date of receipt and reference date of the claim under the contract.

2

Check SOPA endorsement

Check whether the claim is endorsed as a SOPA payment claim triggering statutory deadlines.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 13
3

Verify contract terms

Review the payment clause for claim timing, valuation method, and certification process.

4

Match claim to schedule of rates

Match claimed quantities to the schedule of rates or lump sum breakdown.

5

Verify work completed

Confirm the claimed work has been completed through site inspection or photos.

6

Review variations claimed

Check whether claimed variations have been approved and priced under the contract.

7

Check EOT and delay claims

Review any EOT or delay cost claims for compliance with notice clauses.

8

Deduct retention

Apply contractual retention deductions or trust account deductions.

9

Deduct LDs

Apply any accrued liquidated damages after practical completion.

10

Prepare payment schedule

Prepare a payment schedule stating the scheduled amount and reasons for withholding.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 14
11

Serve payment schedule

Serve the payment schedule within 10 business days to avoid SOPA consequences.

12

Certify payment

Certify the final payment amount for payment by the due date.

When to use

When this checklist applies

Use each month or milestone when reviewing a contractor progress claim.

Common pitfalls

  • Missing the SOPA 10 business day deadline
  • Variations claimed that were never approved
  • Quantities not verified on site
  • Retention not deducted
  • Reasons for withholding insufficient in payment schedule
Use with Quillio

Run this checklist on a real matter

Quillio can review a progress claim, match to the schedule of rates, and draft a payment schedule. See /practice-areas/construction-lawyers or start a free trial.

General guidance for progress claim reviews. Always apply the relevant state SOPA and contract provisions.