Security of Payment payment claim preparation checklist

The Building and Construction Industry Security of Payment Act 1999 (NSW) gives claimants a fast statutory process to recover progress payments. This checklist is for construction lawyers preparing a payment claim.

In short

This is a 12-step checklist for preparing a Security of Payment Act payment claim in NSW. It covers entitlement, reference date, content, service, and follow-up.

Run this checklist with Quillio — free trial
12-step checklist

The checklist

1

Confirm construction contract

Confirm the arrangement is a construction contract covered by the SOPA.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 4
2

Identify reference date

Identify the reference date on which the entitlement accrues under the contract or the Act.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 8
3

Confirm no prior claim on same reference date

Confirm no earlier payment claim has been served on the same reference date.

4

Identify scope of claim

Identify works, goods and services performed up to the reference date.

5

Calculate claimed amount

Calculate the claimed amount by reference to contract rates or reasonable value.

6

Identify contract clauses

Identify the contract clauses supporting the claimed entitlement.

7

Draft payment claim

Draft the payment claim identifying the work claimed and amount sought.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 13
8

Include statutory endorsement

Include the endorsement stating the claim is made under the SOPA.

9

Attach supporting documents

Attach progress claim schedules, photos, measurements, and variation records.

10

Serve the claim

Serve the claim on the respondent per the contract's service provisions.

11

Diarise payment schedule deadline

Diarise the 10 business day deadline for a respondent payment schedule.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 14
12

Plan next steps

Plan adjudication or court proceedings if no payment schedule or payment is received.

When to use

When this checklist applies

Use when preparing a SOPA payment claim on a NSW construction matter.

Common pitfalls

  • Missing reference date entitlement
  • Payment claim served with no statutory endorsement
  • Scope of claim too vague to identify
  • Not diarising the payment schedule deadline
  • Claim served on wrong entity
Use with Quillio

Run this checklist on a real matter

Quillio can prepare a compliant SOPA payment claim and diarise adjudication deadlines. See /practice-areas/construction-lawyers or start a free trial.

General guidance for NSW SOPA payment claims. Always verify against current NSW legislation and case law.