Home / Glossary / Building Disputes (AU)
Glossary

Building Disputes (AU) glossary

Building disputes in Australia span residential defect claims under Home Building Acts, security of payment under construction legislation, and commercial construction disputes resolved through adjudication, tribunals, and courts. The regulatory landscape is state-based, with each jurisdiction having its own regime. This glossary explains the core terms practitioners need.

In short

This glossary covers 40 terms that construction and building lawyers encounter when advising on residential and commercial building disputes in Australia. Each definition references the relevant legislation or tribunal guidance.

Use these terms with Quillio — free trial
39 terms

Definitions

Adjudication

A rapid, interim determination of a payment dispute under security of payment legislation — binding unless overturned by a court or tribunal.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 17

Adjudicator

An authorised person who determines a security of payment dispute — appointed by an authorised nominating authority after an adjudication application is lodged.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 18

ANA (Authorised Nominating Authority)

A body authorised to nominate adjudicators for security of payment disputes — such as Adjudicate Today or Resolution Institute.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 17(3)

AS 2124

A widely used Australian Standard general conditions of contract for construction — specifying roles, variations, defects liability, and dispute mechanisms.

Standards Australia AS 2124-1992

AS 4000

The current Australian Standard general conditions of contract for construction, replacing AS 2124 — commonly used in commercial construction.

Standards Australia AS 4000-1997

Building licence

A licence required to carry out residential building work — issued by state regulators such as NSW Fair Trading, VBA (VIC), or QBCC (QLD).

Home Building Act 1989 (NSW) s 4

Building practitioner

A person registered or licensed to carry out building work — owing statutory duties to the building owner under recent duty of care reforms.

Design and Building Practitioners Act 2020 (NSW) s 5

Claimable variation

A variation to the scope of work that entitles the builder to additional payment — must generally be in writing and approved in advance under the contract and statute.

Home Building Act 1989 (NSW) s 6(2)

Compliance certificate

A certificate issued by a private certifier or council confirming that building work complies with the Building Code of Australia and development consent.

Environmental Planning and Assessment Act 1979 (NSW)

Construction contract

An agreement for the carrying out of construction work or the supply of related goods and services — the prerequisite for security of payment entitlements.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 4

Defect

Work that does not meet the plans, specifications, statutory warranties, or the Building Code — the basis for a defect claim against the builder or developer.

Home Building Act 1989 (NSW) s 18B

Defect rectification order

A tribunal or court order requiring the builder to rectify defective work within a specified timeframe.

Home Building Act 1989 (NSW); NCAT jurisdiction

Defects liability period

The period after practical completion during which the builder must return to rectify defects — typically 12 months under standard contracts.

AS 4000-1997 cl 35

Design and Building Practitioners Act

The 2020 NSW Act creating a statutory duty of care owed by building practitioners to current and future owners for economic loss from defective work.

Design and Building Practitioners Act 2020 (NSW)

Duty of care (building)

The statutory duty owed by building practitioners to owners and subsequent purchasers for defective building work — created by the Design and Building Practitioners Act 2020 (NSW).

Design and Building Practitioners Act 2020 (NSW) s 37

Expert determination

A dispute resolution process where an independent expert makes a binding or non-binding determination on a technical question — commonly used for quantum disputes.

Extension of time

An extension to the date for practical completion granted under the contract for qualifying delay events — the builder must give notice within the prescribed time.

AS 4000-1997 cl 34.3

Home Building Act

The NSW Act regulating residential building work — imposing licensing requirements, statutory warranties, and dispute resolution mechanisms.

Home Building Act 1989 (NSW)

Home building compensation (insurance)

Insurance required for residential building work over $20,000 in NSW — covering homeowners if the builder dies, disappears, or becomes insolvent.

Home Building Act 1989 (NSW) s 92

Latent conditions

Physical conditions on or near the site that differ materially from those that could reasonably have been anticipated — entitling the builder to a variation or extension.

AS 4000-1997 cl 12.1

Liquidated damages

A pre-agreed sum payable by the builder for each day of delay beyond the date for practical completion — must be a genuine pre-estimate of loss.

AS 4000-1997 cl 34.7

Mediation

A facilitated negotiation process commonly required before tribunal or court proceedings in building disputes.

NCAT

The NSW Civil and Administrative Tribunal — hearing residential building disputes under the Home Building Act, including defect claims and payment disputes.

Civil and Administrative Tribunal Act 2013 (NSW)

Occupation certificate

A certificate authorising occupation of a new building or part of a building — issued by the principal certifier after final inspection.

Environmental Planning and Assessment Act 1979 (NSW) s 6.9

Payment claim

A claim for payment served under security of payment legislation — must identify the construction work and the claimed amount, and be served within the prescribed timeframe.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 13

Payment schedule

The respondent's response to a payment claim — indicating the amount the respondent proposes to pay and reasons for any difference. Failure to serve triggers automatic liability.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 14

Practical completion

The point at which the work under the contract is substantially complete, with only minor defects remaining — triggering the defects liability period and release of retention.

AS 4000-1997 cl 34.5

Progress payment

A payment to the builder during the course of the work, typically based on the value of work completed at each claim date.

Building and Construction Industry Security of Payment Act 1999 (NSW) s 8

QBCC

The Queensland Building and Construction Commission — the regulator of the building industry in Queensland, administering licensing, insurance, and dispute resolution.

Queensland Building and Construction Commission Act 1991 (QLD)

Retention

A percentage of progress payments withheld by the principal as security for the builder's obligations — released progressively after practical completion and the defects liability period.

AS 4000-1997 cl 5.4

Scott Schedule

A tabular format listing each defect, the claimant's description and costings, and the respondent's response — commonly used in building defect proceedings.

Security of payment

The statutory regime ensuring persons who carry out construction work or supply related goods and services can recover progress payments — enacted in every Australian jurisdiction.

Building and Construction Industry Security of Payment Act 1999 (NSW)

Statutory warranty

Implied warranties under the Home Building Act that residential building work will be done with due care, be fit for purpose, comply with plans, and be completed within a reasonable time.

Home Building Act 1989 (NSW) s 18B

Superintendent

The contract administrator under AS 2124 or AS 4000 — responsible for administering the contract, certifying payments, and assessing variations and claims.

AS 4000-1997 cl 20

Unfair contract terms

Terms in standard-form building contracts that are unfair under the Australian Consumer Law — void and unenforceable since 2023 amendments.

Competition and Consumer Act 2010 (Cth) Sch 2 s 23

Unlicensed work

Building work carried out by an unlicensed person — the builder cannot enforce the contract and the owner may be entitled to a refund of money paid.

Home Building Act 1989 (NSW) s 10

Variation

A change to the scope, quality, or timing of work under a construction contract — must generally be in writing and may entitle the builder to additional payment and time.

AS 4000-1997 cl 36

VBA

The Victorian Building Authority — the regulator of the building industry in Victoria, administering registration, compliance, and dispute resolution.

Building Act 1993 (VIC)

Warranty period

The statutory period during which a homeowner can make a claim under statutory warranties — six years for major defects and two years for other defects in NSW.

Home Building Act 1989 (NSW) s 18E
Use with Quillio

Research these terms in context

Quillio helps construction and building lawyers research defect claims, prepare Scott Schedules, and draft adjudication submissions with references to security of payment legislation and Home Building Acts. See /practice-areas/construction-lawyers or start a free trial.

These definitions are general explanations for educational purposes — not legal advice. Building dispute law differs between states and territories. Always verify against the current legislation, contract terms, and tribunal practice directions.

Research these terms with citations.

Quillio gives you the term, the current authority, and a clickable citation — all in one place. The free trial requires no credit card and no sales call.

Start your free trial